National Grid’s contractor, Posillico Environmental, is implementing bulkhead barrier wall construction related to the Fulton former Manufactured Gas Plant (MGP) Site in accordance with the EPA-approved design. This project includes replacing approximately 880 linear feet of existing bulkheads along the eastern side of the Gowanus Canal from the canal’s head end (at Butler Street) to the Union Street Bridge. The new bulkhead barrier wall will include steel sheet piling with an anchored support system that has been designed to serve as both an environmental barrier and be able to support the EPA’s planned canal dredging and capping remedy. Mobilization for this phase of the work began on August 28, 2019 and barrier wall construction is currently expected to be completed in late Fall 2020. Community air monitoring and construction monitoring for vibration and movement is being performed throughout the project.
Completed Activities
Pre-clearing the bulkhead alignment of debris and potential obstructions to allow mobilization of equipment to the head end of the canal and facilitate construction of the barrier wall was completed in December 2019. All debris removed during this pre-clearing was deemed to be not culturally significant and approved for off-site disposal by EPA.
Drilling equipment, a specialty barge, and a temporary water treatment system were mobilized to the site in January 2020 to support barrier wall construction activities.
Installation of the sound curtain between Parcel I building (270 Nevins Street) and canal was completed in early January 2020.
Pre-drilling the barrier wall alignment along Parcel VII (234 Butler Street) was completed in early February 2020.
On-Going Activities
- Continued preparation of the upland area for pre-drilling of the bulkhead alignment.
- Pre-drilling the barrier wall alignment using drill rigs along portions of Parcel VI (242 Nevins Street), Parcel I (270 Nevins Street), and 525 Union Street.
- Test pitting for utility locations.
- Air monitoring.
- Movement and vibration monitoring and assessment at Parcels I, VI, VII, 525 Union Street and the head end of the canal.
- Noise monitoring.
- Delivery of project related construction materials.
- Tie-back anchor load testing.
Upcoming Activities
Pre-drilling of the wall alignment within the canal is on-going and it is currently anticipated that this work will be completed in May 2020. Delivery of steel sheet piles to the site and initiation of sheeting installation is currently expected to occur in March 2020.
prada ss 22 prada heeled boots prada cufflinks tod's outlet store tamagotchi toys prada luna black prada sunglasses swirl franchise chicken cartera prada negra 20k instagram followers instagram followers fast prada loafers monolith prada d'iris followers instagram buy velcro board prada print arca prada lyrics prada running shoes crossbody prada bag aws chatgpt prada men's jewelry instagram statistics followers silicone head carlucci restaurant chicago instagram followers 300 500 instagram followers rosemont bars factory online stores fiverr instagram followers prada heritage glasses prada glasses sunglasses prada watch ladies prada bags cost williams chicken locations tamagotchi games lost followers instagram prada bowler bags lentes prada originales chatgpt google sheets outlet prices women's prada necklace womens prada sunglasses prada pet prada sock shoes chatgpt coin gucci prada song prada golf bag prada sungless the gift by aselin debison lyrics prada sonnenbrille prada patterns opoli gilt login openai chatgpt plus urchase instagram followers travel agent slogan prada sunglasses logo academie da vinci prada shearling sneaker platform prada loafers real captains hat prada pattern ship captain uniform prada facemask prada authentication chatgpt access denied怎么解决 velvet prada bag south colby post office prada wicker boat captain shirts yacht club uniforms amanda peet identity prada claw clip prada zip chatgpt excel plugin sheets of cork board prada side purse chatgpt hype long goatees chatgpt stand for prada pictures prada shoes sandals nude prada bag instagram 20k followers paypal instagram followers concepts about print board for wall prada bottle aeropostale outlet mall
Community Air Monitoring Plan Summary
Air quality monitoring is being performed consistent with the Community Air Monitoring Plan (CAMP) for the Fulton Site using a MiniRAE 3000+ PID for volatile organic compounds (VOCs) and TSI Dust Trak DRX Dust Meter. No VOC or dust levels attributable to the barrier wall project have been detected above Action levels during working hours to date.
Pre-drilling Operation from the Jack-Up-Barge along Parcel I.
Pre-drilling Operation from the Jack-Up-Barge along Parcel I.