Update Week Ending June 22, 2012

Pre-Design Investigation

A Pre-Design Investigation (PDI) commenced on June 4, 2012 at the former Fulton Municipal Works MGP. The scope of work is being conducted under a New York State Department of Environmental Conservation (NYSDEC) and New York State Department of Health (NYSDOH)-approved Pre-design Investigation Work Plan (PDI WP). The work will be conducted in and on properties adjacent to the Gowanus Canal, in the vicinity of the former Fulton Municipal Works MGP. The work includes the installation of soil borings, monitoring wells, a utility survey and structural surveys to gather geotechnical data and further define the nature and extent of impacts.

The scope of work is presented in the PDI WP titled Fulton Municipal Works Former Manufactured Gas Plant Site, Final Interim Remedial Measure, Pre-Design Investigation Work Plan, dated March 2012. This document is available in the Key Documents/Major Reports section of this website.

Activities June 18 through June 22, 2012:

  • Completed the pre-clearing of select boring locations east and west of the canal.
  • Completed the accessible delineation borings west of the canal.
  • Continued the geotechnical borings east and west of the canal.

Future (two week look-ahead) activities:

  • Continue the installation of soil borings on properties east and west of the Canal.