Weekly Update – Week Ending April 23, 2010

Remedial Investigation

Remedial Investigation field at the former Fulton Municipal Works MGP is being conducted under a New York State Department of Environmental Conservation (NYSDEC) and New York State Department of Health (NYSDOH)-approved Remedial Investigation Work Plan (RIWP).  The work includes the installation of soil borings, monitoring wells, test pit excavations, and soil vapor points to gather information required to determine the nature and extent of impacts within the footprint of and adjacent to the former Fulton Municipal Works MGP.  National Grid continues to pursue access to complete the remaining proposed RI activities.

Based upon the preliminary findings of the RI completed to date, National Grid and NYSDEC agreed that additional off-site investigations were needed in the vicinity of the MGP.  The off-site work is described in the July 20, 2009 RIWP Addendum.  National Grid completed these additional off-site field installation activities at the beginning of August 2009.
Activities April 17 through April 23:

  • No field activities.

Future (two week look-ahead) activities:

  • Complete utility clearance activities at a private property.
  • Commence the installation of the final proposed RI soil borings at a private property.